Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia
Authors:
- Agnieszka Leśniak,
- Grzegorz Piskorz,
- Marcela Spišáková,
- Daniela Mačková
Abstract
Any construction project, even one that is excellently planned and organized, is prone to the risk of unforeseen events and problems, which in effect can cause late completion of works. The paper presents the results of the research conducted among Polish and Slovakian building contractors. One attempt was to identify and assess the potential causes of delays in the construction works resulting from the provisions of the contract. The knowledge of these factors can help contractors to take protective measures, reducing the risk of delays during the implementation of construction works.
- Record ID
- CUT7d324cec699b426ca0af42da6cb400cd
- Publication categories
- ;
- Author
- Journal series
- Scientific Review Engineering and Environmental Sciences , ISSN 1732-9353, e-ISSN 2543-7496, Quarterly
- Issue year
- 2018
- Vol
- 27
- No
- 1 (79)
- Pages
- 71-81
- Other elements of collation
- tab.; wykr.; Bibliografia (na s.) - 80-81; Oznaczenie streszczenia - Summ.; Numeracja w czasopiśmie - Vol. 27, Iss. 1 (79)
- Keywords in English
- construction works, delays factors, contractors, questionnaire survey
- DOI
- DOI:10.22630/PNIKS.2018.27.1.7 Opening in a new tab
- URL
- http://iks_pn.sggw.pl/PN79/A7/zeszyt79art7en.html Opening in a new tab
- Language
- eng (en) English
- License
- Score (nominal)
- 10
- Additional fields
- Indeksowana w: Scopus
- Uniform Resource Identifier
- https://cris.pk.edu.pl/info/article/CUT7d324cec699b426ca0af42da6cb400cd/
- URN
urn:pkr-prod:CUT7d324cec699b426ca0af42da6cb400cd
* presented citation count is obtained through Internet information analysis, and it is close to the number calculated by the Publish or PerishOpening in a new tab system.